Enter the length, width and thickness of your slab or footing to get the concrete volume and the number of pre-mix bags to buy.
Concrete volume
0.6 m³
Cubic yards
0.78 yd³
Pre-mix bags
65
incl. ~7% extra
Volume = length × width × thickness. Bags from yield (20 kg bag ≈ 0.01 m³); over-order slightly for structural pours. 🔒 In your browser.
How the concrete calculator works
Concrete volume is length × width × thickness. The tool computes it in cubic metres (or cubic feet/yards), then divides by the yield of a pre-mix bag to estimate the bags needed. A little extra is added because concrete settles and spills, and part-bags round up.
Pre-mix bag yields differ: a 20 kg bag makes roughly 0.009–0.011 m³, an 80 lb bag about 0.6 ft³. For anything structural, over-order slightly — running short mid-pour is far worse than a spare bag.
Frequently asked questions
How do I calculate concrete volume?
Multiply length × width × thickness, all in the same units. A 3 × 2 m slab, 0.1 m thick, is 3 × 2 × 0.1 = 0.6 m³ of concrete.
How many bags of concrete do I need?
Divide the volume by the yield of one bag. If a 20 kg bag yields about 0.01 m³, a 0.6 m³ slab needs roughly 60 bags — so for large pours, ready-mix delivery is usually cheaper.
How much extra concrete should I order?
Add about 5–10%: concrete settles, spills and sub-grades are rarely perfectly level. Running out during a pour creates a weak cold joint, so it’s better to have a little spare.
What thickness should a slab be?
It depends on the load — commonly 100 mm (4 in) for paths and patios, more for driveways or structural slabs. Follow local building guidance for load-bearing work.
Does this handle footings and columns?
Yes for rectangular shapes — enter the length, width and depth. For round columns, multiply π × radius² × height separately.
Related home & DIY tools
From the blog
-
How Much Do I Need? Estimating Paint, Tile, Concrete and Mulch
Every home-project estimate is either an area job (paint, tiles) or a volume job (concrete, mulch). Area = length × width; volume = area × depth. The formulas, sensible coverage and waste allowances, and how to turn them into cans, tiles, bags and rolls.
-
Rebar in a Concrete Slab: Spacing, Cover and Lap Splices Explained
Residential slabs typically use #4 bar at 12–18 inches on centre with 3 inches of cover. Here's how to work out bar counts, why cover matters more than people think, and where the '40 bar diameters' lap rule differs from what the code actually requires.